Showing posts with label Engine. Show all posts
Showing posts with label Engine. Show all posts

Wednesday, 26 November 2014

It might be a car one day!

Despite the lack of updates since my last milestone, I have been making progress in a number of areas on the car.

I have started fabrication of the lower radiator pipe (to the water pump) from a collection of stainless bends and straight sections - this is currently tacked up and test fitted to check the clearances and it is ready for fully welding


Installed the four rivnuts which will hold the fan brackets to the radiator


Test fitted all of the metalwork for both doors (hinges, hinge brackets, intrusion beam, lock mounting etc.), bonnet (‘hood’ for subscribers across the pond) and boot.



Most of these were a simple fit, but I had to adjust the boot hinges somewhat. Unfortunately, the only way to tell exactly what adjustments were needed was to fold my 6’2” frame into the boot, then lift the loose panel into plate (with wedges around the opening to make sure it was centralised). Now inside the boot (along with a torch), I could offer up the hinges to their respective mounting points on the boot and see what needed adjusting. It turned out that I needed to adjust the angle of the mounting plate on the end of the metalwork which involved cutting a slit most of the way through the arm, bending it closed then welding it up. This seemed to do the trick so I could disassemble everything and send them all off to be powder coated along with the radiator fan brackets.



Trimmed and filled the remaining seams on the bonnet, boot and door panels. These are substantially complete, but there are a few areas that need more attention.

Moulded the brackets that will mount the bonnet and boot panel gas struts. These were made by setting up a polypropylene barrier in the four locations (2 on each of the panels) and applying a layer of release tape to the fibreglass skin of the bonnet or boot.


I could then gel coat and wet-lay the carbon fibre tape against the barrier and release tape to create a perfectly fitting bracket.

Once cured, I trimmed to shape and bonded in the threaded metal insert that accepts the strut end ball stud. These can then be bonded to their respective panels along with installing the captive nuts in the bodywork to allow the gas struts to be fitted.



Machined the slots for mounting the windscreen / windshield to the body, along with drilling and tapping the mounting points for the two wing mirrors into the two screen pillars.


After test fitting the pillars and screen though, I have noticed quite a large gap (~10mm) on one side at the bottom of the pillar which tapers to essentially no gap where the pillar meets the body. I need to address this as the mounting bolts will no doubt clamp it up tight, but this will stress the windscreen which won’t do it any favours. I am not sure I can straighten the pillar enough without cracking the chrome plating, so a tapered ‘wedge’ may be required

In addition, given the significant lead time, I have now ordered the trim (seats and carpets) – but you will have to wait until the big reveal to find out what colour(s) I have chosen!

Monday, 23 September 2013

Just like buses...

...nothing for ages, then two updates together!

Some of the smaller jobs ticked off the list most recently include finally finding a solution to the thermostat housing problem. Having bought two aftermarket versions (which although nice and shiny, did not fit), I thought I would throw caution to the wind an source a genuine Ford part. Low and behold it dropped straight in with no issues! The only modification I needed was to drill and tap the optional fitting in the top so I could fit a secondary temperature sensor. This will be the sensor to drive the temperature gauge whereas the sensor in the normal position in the manifold will be reserved for the Engine Control Module. It is possible I could have used a single sensor for both, but there were potential buffering and ground loop issues having two processors reading the same sensor so I thought in the interest of fault diagnosis, two was better than one.

Carrying on the sensor theme, I have sourced an oil pressure sensor that GM use on their LS series of engines, and machined up an adaptor to allow connector to the normal ‘idiot light’ switch position on the engine block. As usual, nothing is ever that simple, and clearance to the block meant that the sensor would not simply screw into the same position, so the adaptor also had to relocate the sensor to a remote location. Fortunately, Ford have provided a suitable threaded boss in the water pump for just such an occasion. A short braided hose was also required to connect the two together, so another skill of hose assembly was learned.



The other sensor fitted recently was to read oil temperature. Once again, Ford have been kind enough to provide an easy route in the form of a  secondary drain plug in the sump. This is used to get all of the oil out that would otherwise be trapped by the ‘hump’ of the oil pan that clears the sub frame normally running under the engine. I was able to reverse engineer the thread used on this fitting and machine up an adaptor for the sensor. It is not at the lowest point on the chassis but it is still a little vulnerable, so this will get some kind of skid pan to protect the connector and wiring.


Since the sensors will be read by a microprocessor, I have not been able to use the more typical 1-wire senders as the earth path through the block typically affects the measurements. I have therefore had to use 2-wire sensors which are more difficult to come by, and even harder to find suitable data sheets. Fortunately, the GM LS engines are used quite a lot in aftermarket installations (they will sell a whole crate engine if you want), and more data is available on the spares. I therefore have a Ford engine, but controlled and monitored using GM sensors – fingers crossed they will work together without getting into a fight!

Other progress has been the fitting of the clutch slave cylinder and making up the braided hose for the hydraulic line and I have now collected the rear part of the exhaust from Gardner Douglas. This connecting pipes will need modifying (or replacing) to meet up with my own design headers, but it gives me a head start in terms of known good routing under the chassis and bodywork.



As for the milling machine, I have now connected the motors to the various slides and successfully run through a sample program. There are a couple of parts to finish on the spindle drive and I will then be in good shape to start test cutting.

Tuesday, 28 August 2012

Let the games begin

A bumper update this week thanks to the long weekend. Since receiving the chassis and borrowing a spare bonnet from the kit manufacturer, I have been working away at creating a CAD model. This was finished up to the necessary level ahead of the weekend so I could break out the tools and start building!



The build manual recommends assembling the rear axle off the chassis, then lowering the framework around it. This seemed like a sensible approach, so I made it the first task as manoeuvring a bare chassis sounded easier than moving a partially assembled one. The rear axle is straight out of the donor Jaguar with the lower wishbones pivoted off the differential. This means that the pivot mounting brackets determine the toe and thrust of the rear wheels and have to be carefully aligned with shims. The brackets that hold the assembly into the chassis are drilled to provide the correct alignment (in theory), so I set about mocking up the pivots to determine the correct shims. I will still have to measure the alignment when the axle is complete to finally check the toe and thrust measurements, but this should give me a good start. 


With the shims established, I could fix the lower pivot brackets and make my first attempt at lockwiring the bolt heads, which proved easier than anticipated (when you wrap the wire the correct way around the bolt head!).


 The rest of the rear axle assembly continued as per the Haynes (Chilton) manual including shimming of the rear brake discs (rotors) to centralise them in the callipers and assembly of the rear brake callipers. The assembly of the inner pivot tubes proved to be fun thanks to the multitude of spacers, thrust washers and seal retainers, but the liberal application of grease held everything together long enough to assemble the pivot shaft without a pile of bits on the floor!


At this stage, the driveshafts and rear uprights would be fitted, but as I am still waiting on parts to complete their assembly, I moved on to fitting what I had to the chassis. This was simply a case of lowering the rear of the frame over the assembly and fitting 8 bolts.




With the rear assembly as complete as I could make it, I moved onto preparation for engine installation. This involved fitting the two fuel lines (feed and return for the injection system) along with the brake pipes. The fuel lines were installed using brackets I designed and a work colleague machined for me (thanks Colin), held in with rivnuts. 



The brake lines use a series of push-in clips and these (along with the fuel line clamps) have to be spaced to provide sufficient support as this is inspected at the Individual Vehicle Approval (IVA) test. Most of the fitting was relatively straightforward, however the front brake pipe proved more challenging due to the tortuous route under the engine mounting bracket. Two sore thumbs later and I was ready to fit the engine and gearbox assembly.



The chassis design allows for excellent access for this job and the only hindrance was a lack of manoeuvring space for the engine crane. It turned out to be easier to lift the engine up and slide the chassis under it before rolling the crane (and engine) into place. The engine mounts were bolted into place and the powertrain was in its new home. The gearbox tail housing is currently sat on a piece of wood until I can fabricate the rear mounting bracket.




With the engine installed, I was able to turn my attention to the front suspension. As per the rear axle, this is lifted straight from the Jaguar donor and bolts up to the chassis in the same way. The only real deviation is the bespoke steering arm to suit the new rack as well at the omission of the various shields. This concluded my weekend of construction – not bad for a few days work!



There is still some work to complete the front suspension assembly – making up a new pair of rigid brake pipes from the calliper to the flexible hose as well as setting up the front angles – camber, castor and toe. The geometry will be much easier to work on when I have the steering rack so this will have to wait for suitable funds! At least I can amuse myself with designing the intake system in the mean time.

Monday, 26 March 2012

Driveline

With the engine substantially built (minus the induction system), I have been able to turn my attention to the transmission. When this engine is used in passenger cars and if attached to a manual transmission, the clutch is actuated by a cable. Unfortunately, this is not very Cobra friendly (especially when fitted in a right hand drive car), so the typical approach that my peers take is to fit a hydraulic conversion. Never one to take the easy route, I am working on constructing my own conversion using more readily available parts rather than rely on a £200 ‘kit’ that doesn’t really fit according to some who have used it. To this end, I needed to measure the clutch actuation force at the release (throw out) bearing to allow me to calculate the mechanical advantage and movement required at the pedal. Fortunately, we have a hydraulic press at work which, when coupled to a load cell and dial gauge, proved to be very useful for collecting the required data!


In addition, I was able to complete the fabrication of the engine cradle which allowed me to remove the engine from the build stand and access the rear of the block. This allowed the installation of the final core plug (at the end of the cam shaft) along with the oil gallery plugs.


These were followed by the block plate, flywheel and clutch which then allowed me to ‘dial in’ the bellhousing. This is achieved by fitting a dial gauge to the clutch and measuring the runout of the bellhousing location diameter when turning the crank. The bellhousing is mounted on offset dowels which can be rotated to get the runout below the 0.005” target specified by the transmission supplier.


With this completed, all that remained was to fit the transmission itself which proved to be easier than expected thanks to judicious use of my engine crane to take most of the not insignificant weight! I also fabricated a transmission support ‘foot’ at the same time as the engine cradle to allow the whole driveline assembly to be wheeled about as required. Now all it needs is a chassis around it!

Next steps involve the re-assembly of the donor suspension components for which I am currently collecting all of the new bearings, seals, shims, and fasteners. I now therefore need to switch from the UNC threads used on the engine, to the UNF threads (along with a couple of fine Metric threads for good measure) used by Jaguar in the 60’s. Hopefully I won’t get them mixed up!

Monday, 19 March 2012

Final Engine Assembly

A number of small jobs came together this weekend to see the substantial completion of the engine build (minus the intake manifold because I haven’t started making that yet!).

  • The addition of fuel injection requires a crank position signal so I have designed my own sensor mounting bracket and trigger disc target which were laser cut from steel.
  • The mounting of the trigger disc required me to turn and machine some custom spacers to put the disc in the correct location relative to the sensor as well as aligning the crank pulley with the water pump and alternator.



  • The spacers and fasteners for the alternator mounting needed modifying to suit the particular configuration of my engine which has taken some to-and-fro to get right, but this is now finally fixed.

  •  With the machining carried out on the block, along with the various aftermarket parts used, I needed to check the valve to piston clearances. This involves placing some blu-tack on the top of the piston, fitting the cylinder head and rockers then turning the engine through one complete cycle. The head is then removed and the thickness of blu-tack is measured. I had just enough, so I’m glad I didn’t go for the higher ratio rockers after all!


  • The crank sensor mounting bracket is also the timing pointer so with this finally mounted, I no longer needed access to the pistons (used to determine Top Dead Centre for fine tuning the timing pointer position) and could install the cylinder heads, rockers and covers.


The next task is to align the bellhousing and the fit the gearbox which cannot be done on the engine stand, so I have started fabricating an engine cradle. This picks up on the engine to chassis mounting points which will allow the engine assembly to sit on castors and crucially frees up the gearbox mounting bolts for adding the rest of the driveline. So far, I have tacked the structure together and test fitted the basic frame - this then needs to be fully welded and the wheels added before it can be pressed into service.


Once this is complete, I can move on to rebuilding the donor suspension components.

Monday, 23 January 2012

Engine build continues

It has been some time since my last update, mainly because it has been some time since I made any progress. However, the planets aligned this weekend and I hade the time available, the appropriate tools to hand and most importantly, the weather smiling on me so I could continue the engine build.

First task was to measure the endfloat of the camshaft and crankshaft as these values are critical for proper lubrication.


Pressing my new Dial Test Indicator (DTI) into service, I was able to check that these measurements were within specification and so could move onto ‘degreeing’ the camshaft. For those unfamiliar with the job, this means checking the cam timing against the crank angle and involves fitting an angle gauge to the crank (aligned with number 1 piston) and measuring the angle of maximum lift of the corresponding intake and exhaust tappets (lifters). These angles may not be quite as the manufacturer intended due to component tolerances of the specific engine being built and there is an amount of adjustment in the system to allow for compensation.

My cam timing came out to be around 1.5 degrees late, but since the three adjustment positions I had available it 0, +4 degrees or -4 degrees (I have not seen a vernier cam sprocket for these engines that will fit under the stock timing cover), this was a close as I was going to get! Next up was fitting the oil pump which needed modification in order for the mounting bolts to sit flat. Fortunately, the milling machine at work had been available for such a job and made light work of the task.


Fitting the oil pickup pipe finished off that part of the assembly and with one last torque check of the bolts, I could move onto closing up the oily bits of the engine.This started with the timing chain cover then the sump followed by the water pump. These were relatively simple tasks, but since I am using a random collection of original equipment, reproduction and aftermarket parts, some of the fastener kits don’t have the correct bolts so I need to purchase some additional hardware before I can finish this off.




I am now at the stage where I need to procure the parts I have designed for adding the fuel injection components before I can progress the engine build any further. I suspect it may be a little while before the planets align again, so it is not too much of a rush!